Assume that we have a resource "Manhour".
This resource is available 100% during the summer period but it is available only 50% during the winter period.
By using resource calendar I could only change the working or nonworking days for that resource. But I want to change just the available resource rate for a given period? But how?
I have to show the resource S curve for summer and winter periods to our client.
Regards
Assume that we have a resource "Manhour".
This resource is available 100% during the summer period but it is available only 50% during the winter period.
By using resource calendar I could only change the working or nonworking days for that resource. But I want to change just the available resource rate for a given period? But how?
I have to show the resource S curve for summer and winter periods to our client.