I just move from P3 3.1 to P3 E/C 5.0. In 3.1 it is very easy to set the physical progress on baseline bar, but in 5.0 I set the progress bar same row position as baseline but the start point is not same as baseline start point and just start same as current bar start point, so the physical progress just in the middle of baseline bar. How can i do?