Im really hoping someone can help me with this one. Ive seen P3 do some odd things before but Ive never seen it do this before. I had a MSProject03 file that I converted to a .MPX file and then converted to a P3 file. After checking that the logic transfered correctly, recoded the entire database, changed all of the activity types to Tasks & made all of the resources non-driving, I changed the data date and hit F9. The data date moved but it didnt push any of my activities. Now I have unactualized activities to the left of the data date. Also, I removed a few SNET constrants and when I calced they slammed all the way back to the project start date - about a month prior to the data date.
Anybody got any thoughts???