Hi everyone,
I have another problem. I remember in P3 3.1 we used to organze/group activities by resources and add one column for budgeted units to modify the resource units for each activity in the main layout.
I am not able to do this in P5. In the activity detail window, resources tab there is one column named "budgeted units". Can I bring this column to the main layout after grouping activities with respect to resources?
Any help is greatly appreciated.
Thanks,
Zafar