Hi to all PP Members
I am new in planning works, I would like all experienced planners to give contribution in my subject Sequence of Trades .
Example:
Project : Building Construction Logic Tips sequence
1. The rough plumbing, steam fitting, wiring, and ventilation should be installed as soon as the rough framework of the building is available to work upon.
2. The finish plumbing, heating, and ventilating work should be usually installed after the completion of the finished plaster, floor, and marble work.
3. Concrete pouring --FS+lag--Stripping
Thank you hope every body would contribute.
I am new in planning works, I would like all experienced planners to give contribution in my subject Sequence of Trades .
Example:
Project : Building Construction Logic Tips sequence
1. The rough plumbing, steam fitting, wiring, and ventilation should be installed as soon as the rough framework of the building is available to work upon.
2. The finish plumbing, heating, and ventilating work should be usually installed after the completion of the finished plaster, floor, and marble work.
3. Concrete pouring --FS+lag--Stripping
Thank you hope every body would contribute.