When using the leveling tool in Primavera (release 5.0) there is a significant difference in the project end date and activity task start and finish dates when the "preserve schedule early and late dates" option is selected.
How do I know to utilize this option or not, it prolongs the project by 2 months, but when the option is not chosen the project ends earlier. There is not an over allocation of resources that I can see when the option is not selected, but I do not understand what the program is doing differently when the option is selected or not.
Paula
How do I know to utilize this option or not, it prolongs the project by 2 months, but when the option is not chosen the project ends earlier. There is not an over allocation of resources that I can see when the option is not selected, but I do not understand what the program is doing differently when the option is selected or not.