I am importing a consultants MS Project schedule into Primavera Contractor. The costs for each activity import into "expenses." I need to convert the expenses into resources so I can run resource reports.
Contractor wont import/export to a spreadsheet, so I cant do it that way.
Any ideas?
Thanks!
Contractor wont import/export to a spreadsheet, so I cant do it that way.
Any ideas?