Hi All,
Im using budget cost as the weight factor for % complete calculation.
Now I have to include more detailed activities into the schedule. Im thinking of changing the current activities to hammock activities summarizing the detailed activities.
This way I will only track progress on the detailed activities. EVA will be done based on earned value of the hammock activities. Actual percent complete of the hammocks can be adjusted with unlinked rem. duration/schedule percent complete.
Do any of you have experience with this approach, is it recommendable?
Your ideas will be very much appreciated.
Thanks!
Heinz
Im using budget cost as the weight factor for % complete calculation.
Now I have to include more detailed activities into the schedule. Im thinking of changing the current activities to hammock activities summarizing the detailed activities.
This way I will only track progress on the detailed activities. EVA will be done based on earned value of the hammock activities. Actual percent complete of the hammocks can be adjusted with unlinked rem. duration/schedule percent complete.
Do any of you have experience with this approach, is it recommendable?
Your ideas will be very much appreciated.
Thanks!
Heinz