I am using MSP Standard 2002. I have encountered the following problems with SS and FF links:
a. Finish to Finish Link: Predecessors calendar is transferred to the Successor.
b. Start to Start Link: When an activity has got only a "successive Start to Start Link", as soon as "Actual start" (or % complete) is entered it becomes an open end activity. (Total float calculates up to the project end date)
Can anyone explain/ help as how to resolve?
Regards
Viraja Leelaratna
a. Finish to Finish Link: Predecessors calendar is transferred to the Successor.
b. Start to Start Link: When an activity has got only a "successive Start to Start Link", as soon as "Actual start" (or % complete) is entered it becomes an open end activity. (Total float calculates up to the project end date)
Can anyone explain/ help as how to resolve?
Regards
Viraja Leelaratna