Hello planners!
Ive hit a problem with a sub-contractor, who is not a planner.
Im using MSP2003 and thought he was also, so I made it easy for him to update his plan by telling him to use the "Move start of the remaining parts before status date forward to status date" function, however he uses MSP2000 and it doesnt appear to have this function.
Is there a simple way to do this in MSP2000?
Thanks,
Scott.