In using a simple abbf analysis how would you handle the subject of construction drawing issues?
For example imagine an activity was planned to take 6 weeks but actually took 12 weeks to complete. During the currency of the activity there were several drawings issued from the design team.
Then suppose the activity is 1st fix electrical and the drawings are for floor boxes, containment and high level trays.
Planned: xxxxxx
Actual: xxxxxxxxxxxx
Drawing issues: x x x x
With such a mis-match in the basic level of detail for the as-built construction activity, compared to the high level of detail for the drawing issues; is it possible to use the abbf method?
What do you think PPers?
For example imagine an activity was planned to take 6 weeks but actually took 12 weeks to complete. During the currency of the activity there were several drawings issued from the design team.
Then suppose the activity is 1st fix electrical and the drawings are for floor boxes, containment and high level trays.
Planned: xxxxxx
Actual: xxxxxxxxxxxx
Drawing issues: x x x x
With such a mis-match in the basic level of detail for the as-built construction activity, compared to the high level of detail for the drawing issues; is it possible to use the abbf method?
What do you think PPers?