All,
For some reason I cant get this to work.
Quite simply all I want to do is to increase the duration of an activity then the budgeted quantity of the resouce increase accordingly.
E.g.
Duration 40d
Resource 40days work
Change:
Duration 42d
Reource to increase 42 days work i.e. Unit per day to stay at 1!!
Any help with the rules?
CM
For some reason I cant get this to work.
Quite simply all I want to do is to increase the duration of an activity then the budgeted quantity of the resouce increase accordingly.
E.g.
Duration 40d
Resource 40days work
Change:
Duration 42d
Reource to increase 42 days work i.e. Unit per day to stay at 1!!
Any help with the rules?