I tried merging two P3 files - each with a different planning unit i.e., one has "Weeks" and the other has "Days".
I first copied the file with "Weeks" and changed its unit to "Days". I used this copied version as the host and brought in the file with "Days".
P3 did not convert the host files "Weeks" to "Days". The numeric value of the OD remained unchanged but with different units. This doesnt serve me any purpose.
e.g., 1 week became 1 day and NOT 5 work days.
Is there a way to have P3 convert the OD automatically from weeks to days (assuming the default Cal #1)?
Thanks,
Kashyap
I first copied the file with "Weeks" and changed its unit to "Days". I used this copied version as the host and brought in the file with "Days".
P3 did not convert the host files "Weeks" to "Days". The numeric value of the OD remained unchanged but with different units. This doesnt serve me any purpose.
e.g., 1 week became 1 day and NOT 5 work days.
Is there a way to have P3 convert the OD automatically from weeks to days (assuming the default Cal #1)?