A contractor is entitled to the benefit of any float within an as-planned programme, when the programme is incorporated in the contract as a Contract Document.
Accordingly, the Impacted As-Planned delay analysis technique is the most appropriate method of calculating any entitlement to an extension of time, in those circumstances.
Does anybody dissagree?
Accordingly, the Impacted As-Planned delay analysis technique is the most appropriate method of calculating any entitlement to an extension of time, in those circumstances.
Does anybody dissagree?