Hi,
P3 made our Project Managers used to see the no of equipement i.e Truck, Dozers etc right under the Bar Chart. Now with this P3e/c i am unable to show the peak(UPT) of each resource in the resource spreadsheet. I have tried average but it is quite deceptive and is not producing the same results.
I was wondering if someone might have found some way around.