I have V5 set with all resources and Price/Unit filled in.
When I import a project having no actuals, from P3, Resource/time, Price/Unit are showing something wrong.
Resource / TIme: Some activities are with 0%, some with 18%, some with 100%
Price / Unit: The imported activities are having different price / Unit instead of taking what is set in global price/unit.
Also, I have an activity A and B both with durations 2 Days.
I have given relations A FF 2 B means B is completing after 2 days of completion of A.
But after scheduling A and B are completing on same day.
What to do??
I have V5 set with all resources and Price/Unit filled in.
When I import a project having no actuals, from P3, Resource/time, Price/Unit are showing something wrong.
Resource / TIme: Some activities are with 0%, some with 18%, some with 100%
Price / Unit: The imported activities are having different price / Unit instead of taking what is set in global price/unit.
Also, I have an activity A and B both with durations 2 Days.
I have given relations A FF 2 B means B is completing after 2 days of completion of A.
But after scheduling A and B are completing on same day.
What to do??