If the client gives approved as noted status on the contract program with major comments like the program should be co-ordinated at a latter stage with other contractors who are expected to be onboard at a latter stage of the contract,accordingly the dates ,floats etc of the approved as noted program to be adjusted at a latter stage while maintaining the contract milestone.In case of disputes can the contractor use the approved as noted programs without implementing the clients remarks for making timeimpacts,or the contractor have to comply with the clients remarks and the finally approved program only can be used for assesing time impacts