Hi, in Tools->Options->Earned Value, P3 asks "when calculating earned and planned values, use the budget from?", and then gives two options: 1) Current project, 2) Target Project. By default, the current project is selected. Theory says that we use current projects and target projects in order to measure performance. So, if we are going to use current project and not the target, isnt this a contradiction? shouldnt the target project be selected by default? If the target project is not selected, then why do we create one? Ill wait for the comments of the experts. Thank you.