I have been amending a copy programme to suit a new project, which has some repeated sections of work. The first thing I have done is amend the project WBS, deleting some branches and renumbering others.
The activity numbering has now changed within the project and I now have many activities with different activity names, but the same ID. As many as four, activities have the same ID. Some are sitting within the same WBS section, others in different sections.
How can this happen? What is the best way to sort this out?