Hi every one,
Ive been trying pretty hard lately to compare progress between target project and actual one and I still cannot.
I tought I could show target Resource percent complete and Resource percent complete, then substract one from the other thru Global change after creating a custum data item, and finally filter all lines not equal to 0.
I cannot get a Target resource percent complet in the Global change dialog box, so Im stopped.
Any solution?
Thanks in advance