Does anyone have any experience of an Engineer who requires the Contractor to agree the format of the Interim Payment Application.
I have some problems producing the amount of detail that the Engineer requires as evidence of works completed on my current project.
We have asked him what documents he requires and his response has beeen As an experienced contractor you should know what details are required". To wit the documents required change every month and are used as a dealying tactic in the payment process.
We are now preparing more and more documents every month and provide a document that resembles a VERY detailed final account.
Anyone have any advise on how to deal with this issue.
I have some problems producing the amount of detail that the Engineer requires as evidence of works completed on my current project.
We have asked him what documents he requires and his response has beeen As an experienced contractor you should know what details are required". To wit the documents required change every month and are used as a dealying tactic in the payment process.
We are now preparing more and more documents every month and provide a document that resembles a VERY detailed final account.
Anyone have any advise on how to deal with this issue.