Has anyone encountered a problem with a fixed duration task, what is happening is that I have a task that is fixed duration non effort driven for 50 days I then assign resources at let us say with 50 hours of work, it then populates out the 50 days with 1 hr work per day. But once the first actuals are accepted through Project Web Access then all the remaning work for that resource is lumped into the next day. to fix I have to remove the remaning work and then re type it in, then it is once again levelled over the remaning duration.
Any help would be appreciated G.
Any help would be appreciated G.