Forum Colleagues,
Here’s a brain tickler. This is not a planning question, but more software specific.
To answer my question, a brief intro & cross reference to MS Project is necessary.
In MS project, if we go to FORMAT > BAR STYLES, it is possible to make the % Complete for each activity appear below the activity bar ( Specify ‘Row’ = 2 for ‘Progress’) .
My problem is that I have been asked to produce a similar layout in Primavera (Activity bar on top & % complete as a bar below the Activity bar).
I would really appreciate a prompt response, as I need to produce the first report by tomorrow.
Many thanks in advance !
Here’s a brain tickler. This is not a planning question, but more software specific.
To answer my question, a brief intro & cross reference to MS Project is necessary.
In MS project, if we go to FORMAT > BAR STYLES, it is possible to make the % Complete for each activity appear below the activity bar ( Specify ‘Row’ = 2 for ‘Progress’) .
My problem is that I have been asked to produce a similar layout in Primavera (Activity bar on top & % complete as a bar below the Activity bar).
I would really appreciate a prompt response, as I need to produce the first report by tomorrow.
Many thanks in advance !