Hi, PP people,
Ive created an S Curve (Plan vs Actual using manhours) after everybody agreed with the schedule. Now after halfway, we noticed that we are slipping back. The management decided that I need to create a new S Curve based on current progress since current early finish vs baseline early finish going to be about 10 to 15 days different.
My question,
1. How do I created a new S Curve based on current MS Project data?
2. My idea is to filter only "Incomplete Task" in Task Usage view, copy the manhours and plot a new S Curve. Is this the right way to do it?
3. How do you cope (in terms of reporting of Plan vs Actual % )with changing in schedule?
Hope somebody out there have encounter the same problem that I have.
Thank you.
Ive created an S Curve (Plan vs Actual using manhours) after everybody agreed with the schedule. Now after halfway, we noticed that we are slipping back. The management decided that I need to create a new S Curve based on current progress since current early finish vs baseline early finish going to be about 10 to 15 days different.
My question,
1. How do I created a new S Curve based on current MS Project data?
2. My idea is to filter only "Incomplete Task" in Task Usage view, copy the manhours and plot a new S Curve. Is this the right way to do it?
3. How do you cope (in terms of reporting of Plan vs Actual % )with changing in schedule?
Hope somebody out there have encounter the same problem that I have.
Thank you.