Just wanted to put the question out to all you Planning Planeteers to get some feedback.
How do you guys handle activities that require plant/equipment shutdowns?
Do you create callendars for each piece of equipment showing working days only for scheduled outages?
I doubt this would be suitable as the number of calendars required would greatly exceed those available in P3 (3.1)
any ideas / methods?
// I want to be able to see the real float on shutdown activities... currently for me this is a manual process, knowing all the available windows and when the activity needs to be completed (late finish)
How do you guys handle activities that require plant/equipment shutdowns?
Do you create callendars for each piece of equipment showing working days only for scheduled outages?
I doubt this would be suitable as the number of calendars required would greatly exceed those available in P3 (3.1)
any ideas / methods?
// I want to be able to see the real float on shutdown activities... currently for me this is a manual process, knowing all the available windows and when the activity needs to be completed (late finish)