Hi folks
how can you have remaining duration without having to give % complete, (task dont have a resources)
example:
civil works: on data date: 10NOV09
early start: 10NOV09
early finish: 20NOV09
OD=10days RD=10days
civil works: on data date: 15NOV09
Actual start: 12NOV09
early finish: 24NOV09
OD=10days RD=10days
how can you explain this ????
how can you have remaining duration without having to give % complete, (task dont have a resources)
example:
civil works: on data date: 10NOV09
early start: 10NOV09
early finish: 20NOV09
OD=10days RD=10days
civil works: on data date: 15NOV09
Actual start: 12NOV09
early finish: 24NOV09
OD=10days RD=10days
how can you explain this ????