If we use duration to calculate the physical work progress at site, which is the best way to calculate the delay. Is it Total Float or Variance Early Finish?
When with contractor, contractor has mentioned that the float is belong to them and they can use it to manipulate the delay.
At present I am with consultant. Consultant has different view. The float is belong to consultant and contractor shall use variance early finish to calculate the delay without any manipulation.
Which is the right method and who are right.