Now Im preparing Progress Measurement Procedure, For Engineering, I planned to use estimated man-hour for discipline wise or (Level 3) calculation, i.e. process, mechanical, equipment,.etc. While I use cost for Level 2. For Procurement (Eq. & Matls) Phase, Ill use equipment cost. On a separate category, i.e. Procurement Service, Ill use man-hour for purchasing, expediting, & transportation.
Now, Id like to ask your opinion especially for engineering, with the above method, will it compute/result for the actual progress of engineering? There are instances like for process this cost As we will usually have process engr which spend fews but cost a lot compare to drafters who usually spend a lot of hours but cost a little less than the process engineers.
Now, Id like to ask your opinion especially for engineering, with the above method, will it compute/result for the actual progress of engineering? There are instances like for process this cost As we will usually have process engr which spend fews but cost a lot compare to drafters who usually spend a lot of hours but cost a little less than the process engineers.