1. I am preparing a cash flow histogram for a project with P3, and would want the values to appear ontop of the bars. I cannt get it from Resource/Cost Profile. Any help?
2. It seems P3 is unable to aggregate parallel activities within a time period. It seems to pick only the weightings of the activity that appears first on the schedule.
Would appreciate assistance from any of you P3 experts. Much thanks.