Hi there,
I have built a hammock activity in my planning to host the project management work; one resource is allocated there 1h/d.
When I update the project with Update Progress, the hammock ES date moves forward to the data date; I tried to enter an Actual Start date before launching the 1st Update Progress, with the same result: Actual Start moves to the data date.
Where is my mistake?
Thanks,
Alexandre
I have built a hammock activity in my planning to host the project management work; one resource is allocated there 1h/d.
When I update the project with Update Progress, the hammock ES date moves forward to the data date; I tried to enter an Actual Start date before launching the 1st Update Progress, with the same result: Actual Start moves to the data date.
Where is my mistake?
Thanks,
Alexandre