Hi,
I have a problem in which there is a contractor delay and employer delay for a particular activity. Both these have independent critical path delays (negative total float). TF of employer delay is less than that of contractor though both are negative. (say -25 for employer activity and -50 for contractor activity).
Can the employer ask for EOT and apportionment from employer in this case.
sooraj
I have a problem in which there is a contractor delay and employer delay for a particular activity. Both these have independent critical path delays (negative total float). TF of employer delay is less than that of contractor though both are negative. (say -25 for employer activity and -50 for contractor activity).