Dear fellow planners
Please comment on the following issue:
26 months building construction contract (Start 2 Jan 04, End 2 Feb 06).
Now is approximately 11th month, the project status based on Approved Baseline is -69 days (4 April 06 projected completion).
Various delays encountered, prospective time analysis based on 11th month done.
Projected completion as a result of the added delays is now 3 May 06.
This is 98 days from original contract completion.
1. FROM THE BUILDER’S SIDE, SHOULD I CLAIM THE FULL 98 DAYS OR 29 DAYS (98-69)?
2. HOW DO YOU VIEW THIS IF YOU ARE ASSESSING THIS CLAIM FROM THE CLIENT SIDE, WHAT IS THE ENTITLEMENT?
3. IS THERE ANY GUIDELINE FOR ASSESSMENT OF THIS?
Appreciate comments from all
Please comment on the following issue:
26 months building construction contract (Start 2 Jan 04, End 2 Feb 06).
Now is approximately 11th month, the project status based on Approved Baseline is -69 days (4 April 06 projected completion).
Various delays encountered, prospective time analysis based on 11th month done.
Projected completion as a result of the added delays is now 3 May 06.
This is 98 days from original contract completion.
1. FROM THE BUILDER’S SIDE, SHOULD I CLAIM THE FULL 98 DAYS OR 29 DAYS (98-69)?
2. HOW DO YOU VIEW THIS IF YOU ARE ASSESSING THIS CLAIM FROM THE CLIENT SIDE, WHAT IS THE ENTITLEMENT?
3. IS THERE ANY GUIDELINE FOR ASSESSMENT OF THIS?
Appreciate comments from all