Hi Planners
Is it possible to have Variance Target1 Early finish in calendar days instead of working days ?
For example one project was suppose to complete on 18 Dec 2004 but now it is completing 1 Jan 2005 the total float column is showing -12 days and Variance target 1 early finish column is also showing -12 days. I just want to show the number of days delayed not "working days" delay.
Thanks.
Is it possible to have Variance Target1 Early finish in calendar days instead of working days ?
For example one project was suppose to complete on 18 Dec 2004 but now it is completing 1 Jan 2005 the total float column is showing -12 days and Variance target 1 early finish column is also showing -12 days. I just want to show the number of days delayed not "working days" delay.
Thanks.