Dear Planners
I have a programme with some of the activities are scheduled as Start to finish activities.
e.g. the predecessor for activity no. 1 is start to finish activity from activity no. 2. Now activity no. 1 does not have any successor, as its successor is activity no. 2 which cant be put as successor here because it will then become a loop. Hence the float for activity no. 1 will be until the end of the project.
Can anyone advise how to remove this float and what successor should be assigned to activity no. 1?
Asif
I have a programme with some of the activities are scheduled as Start to finish activities.
e.g. the predecessor for activity no. 1 is start to finish activity from activity no. 2. Now activity no. 1 does not have any successor, as its successor is activity no. 2 which cant be put as successor here because it will then become a loop. Hence the float for activity no. 1 will be until the end of the project.