Hi all,
How can I get P3 to calculate the "duration" of an activity that is linked by a SS and FF relationship?
For example:
Act 1 - start - 1/1/04, Finish - 20/1/04
Act 2 - I dont want to insert the duration for this activity; instead, I want P3 to calculate the same based on a SS and FF relationship with Act 1(assuming no lag). So whenever I change the start, finish dates or duration of Act 1, Act 2 should be adjusted accordingly. Is this possible to do in P3?
Regards,
N.M.Raj