We are currently using P3 to plan our project and sub-projects, but my boss is looking to run MS Project (rather than say SureTRAK or P3) for the sub-projects which will then be run and monitored by the area offices.
We currently have 9 calendars and 60 resource groups in P3 does anyone know if MS Project can cope with this or what its maximum number MS Project can have?