Hi guys,
Using P3 can someany one suggest me how to distribute the resource working on several activities in the same time & same project. If an activity has estimated for hours 135 and requires to completed in 30 days and resource available to work for that activity is 3 hours/day upto 15 days and then start working 5 hours on that activity for 10 days and finally full working day(8 hours) for rest 5 days. Is that my question is clear?
Using P3 can someany one suggest me how to distribute the resource working on several activities in the same time & same project. If an activity has estimated for hours 135 and requires to completed in 30 days and resource available to work for that activity is 3 hours/day upto 15 days and then start working 5 hours on that activity for 10 days and finally full working day(8 hours) for rest 5 days. Is that my question is clear?