A contractor applied for an EOT of 150 days, I have awarded them an extension of only 100 days which I believe to be a fair assessment although they are not in agreement. I have asked the contractor to revise their programme based on the extended period of 100 days however they have refused. The project is now proceeding with the original programme clearly out of date and no real way of monitoring the works. Its a Fidic 1987 contract.
Any ideas as to how I can insist that the contractor updates the contract programme to reflect the additional 100 days?
Any ideas as to how I can insist that the contractor updates the contract programme to reflect the additional 100 days?