Hi all;
Can any body tell me a reference to calculate the required manhour to erect piping spool per linear meter. Avtivities are:
-Erection,Tack
-Welded/Bolted
-Supported
-Inspection (RT,PT,---)
-Pressure Test
-Flushing
-Reinstatement
Thanks to all;
Can any body tell me a reference to calculate the required manhour to erect piping spool per linear meter. Avtivities are:
-Erection,Tack
-Welded/Bolted
-Supported
-Inspection (RT,PT,---)
-Pressure Test
-Flushing
-Reinstatement