Our client instructed us to give acceleration cost of 12 months for a project having total duration of 18 months becuase he wants to complete it within 12 months instead of 18 months.
Also note that project was started just two months before.
For above acceleration of 12 months I prepared following attachments :
a) Baseline schedule (Accelerated schedule for 12 months)
b) Additional cost for Resources (Manpower , Equipment etc)
c) Additional cost for Asphalt Plant
From Presentation point of view to Client, suggest me others points/attcahment /steps to present it before the Client for its acceptance?