I need to collect different Ideas about this Issue:
Say we are in the Middle of a Project and for some reason the Project Scope has been changed by the Owner,and according to that we have to make another Baseline or Target Project..because we add or change some activities in the schedule.
The Question is:
1-Do we need to remove the %progress that we put in the
ongoing project ..and then add the necessary activities
for the new base line?
2-Or shall we build the new baseline from the last point of
the updated schedule..I mean we will leave every thing as
is and just we will add the new activities.
3-Or it is the same whether we use method 1 or 2..it will
lead to the same 2nd Baseline
I need some Invistgation from my brothers the Planners.To fix our understanding to this Important Point
thanks
Ali
=======================================================
Say we are in the Middle of a Project and for some reason the Project Scope has been changed by the Owner,and according to that we have to make another Baseline or Target Project..because we add or change some activities in the schedule.
The Question is:
1-Do we need to remove the %progress that we put in the
ongoing project ..and then add the necessary activities
for the new base line?
2-Or shall we build the new baseline from the last point of
the updated schedule..I mean we will leave every thing as
is and just we will add the new activities.
3-Or it is the same whether we use method 1 or 2..it will
lead to the same 2nd Baseline
I need some Invistgation from my brothers the Planners.To fix our understanding to this Important Point
thanks
Ali
=======================================================