Has anyone out there used the Plannin Planet rates on a real Tender / Contract / Job ?
If so did or how did you qualify them ?
Would like to know, as I have had a bit of debate in the past about actual functional use of said rates.
And personally would not have much confidence unless qualification was attached.
e.g. If I said I could do Six Piles a day, what would that mean 2 U?
With a Rig ?
With a Tripod ?
How many Rigs / Tripods etc ?
What diamater ? Deptht ?
With / without tubes / cages etc. etc etc.???
Know what I mean, or do I need to qualify further?
Comments please.
D.
If so did or how did you qualify them ?
Would like to know, as I have had a bit of debate in the past about actual functional use of said rates.
And personally would not have much confidence unless qualification was attached.
e.g. If I said I could do Six Piles a day, what would that mean 2 U?
With a Rig ?
With a Tripod ?
How many Rigs / Tripods etc ?
What diamater ? Deptht ?
With / without tubes / cages etc. etc etc.???
Know what I mean, or do I need to qualify further?
Comments please.
D.