Hi,
I am trying to add activities to P3e using VBA via SDK. However, after having done "insert into task (wbs_id) values (xxx)", it takes exactly 30 secs for the new activity to be reflected in P3e client (by doing F5-Refresh).
How do I decrease this delay?
I have tried setting "DelayedLoadMode=off" in PMSDK.ini, but this doesnt do the trick.
Any ideas?
Gaultz
I am trying to add activities to P3e using VBA via SDK. However, after having done "insert into task (wbs_id) values (xxx)", it takes exactly 30 secs for the new activity to be reflected in P3e client (by doing F5-Refresh).
How do I decrease this delay?
I have tried setting "DelayedLoadMode=off" in PMSDK.ini, but this doesnt do the trick.
Any ideas?
Gaultz