Dear Specialists,
Can you advise me How can the Late dates be Early than the Earlier dates .
I think the problem lies in the Constraints placed or with the Hammock activities.
Please advise , cos the more such anomalies there are the more wayward it drives me towards the TOTAl float and as such the Critical path may not show the true nature of criticality.
Cheers
Bye
Thanks in Advance.
Nishikant
Can you advise me How can the Late dates be Early than the Earlier dates .
I think the problem lies in the Constraints placed or with the Hammock activities.
Please advise , cos the more such anomalies there are the more wayward it drives me towards the TOTAl float and as such the Critical path may not show the true nature of criticality.
Cheers
Bye
Thanks in Advance.
Nishikant