Could anybody please explain to me the method of incoporation of weighting factors into P3 programme .
add to it , if i also need to display planned quantities upto say 31DEC02 to be displayed in my schedule.
i have tried doing it with CDI,GLobal Change but nothing seems to work.
The weight factors i presumed were derived from cost and quantities at each section of work and each phase of the work scheduled.
Could anyone help me in this context as i have been trying this for quite some time and running short of time.
Thanks in Advance.
Nishikant