I have a project which is Organised and Group By "Project" with the "Total" selected in order to show the total % completion for the overall project during each weekly reporting.
During each weekly reporting, I will update the project data and rescheduled the project (by pressing F9) before printing the schedule in pdf file for emailing to my client.
However I noticed that the Project % (% Complete column) shows different percentage value each time I pressed F9 button! The percentage value will only "stabalised" and show consistent value after a few time pressing the F9 button. If I am not carefull I sometime emailed to my client a report which shows incorrect project % completion.
Any clue to what is happening?
Thanks and best regards,
CS Ong
During each weekly reporting, I will update the project data and rescheduled the project (by pressing F9) before printing the schedule in pdf file for emailing to my client.
However I noticed that the Project % (% Complete column) shows different percentage value each time I pressed F9 button! The percentage value will only "stabalised" and show consistent value after a few time pressing the F9 button. If I am not carefull I sometime emailed to my client a report which shows incorrect project % completion.
Any clue to what is happening?
Thanks and best regards,
CS Ong