1)From my original baseline programme,the structural works is a critical activities & total float is 0 day float.
2) When i update my baseline file as per schedule by using the commands, tools->Update Progress->
>enter the cut off date. After i update it & then i run scheduling.i found that 6 numbers of critical activities which are in front of data date line on the screen and total float is more than 0day!but the remaining critical activities still remain 0 day total float. so the early finish date is remain same!
3) can anyone answer me, what wrongs to my programme. If u require the programme to test, please give me your email address,thank you.
2) When i update my baseline file as per schedule by using the commands, tools->Update Progress->
>enter the cut off date. After i update it & then i run scheduling.i found that 6 numbers of critical activities which are in front of data date line on the screen and total float is more than 0day!but the remaining critical activities still remain 0 day total float. so the early finish date is remain same!
3) can anyone answer me, what wrongs to my programme. If u require the programme to test, please give me your email address,thank you.