Whilst the planner produces an integrate ovetall schedule using a software package to meet the contract spec at level 3 all the other disciplines have to do there own detailed planning Level 4/5 within the parameters of the schedule. They use excel spreadsheets, to do lists, diaries etc.
What are the key activities that should be shown on the level 3 schedule to ensure alignment for:
Quality
Design
Procurement
Subcontracts
Construction
Commissioning