Dears,
I know I should avoid mandatory constraints, but the client forces the team to use a mandatory finish milestone (Project Finish Date) that leads to negative lag. Our mandatory finish constraint on “Project Finish Date” caused a network logic violation, where the successor completes before the predecessor.
I want to know if there is any way that all preceding activities fall into line before the “Project Finish Date”?
Thanks