I dont know if I understood your requirement correctly. Let me put it this way, - you need to have the critical activities one after the other arranged in terms of the early start/ finish dates.
This can be done by
1.Format - organize - Select activity data item - then remove all items under heading group by
2.Under sort by - selct early start or early finish - order by ascend or descend
3. go to filter - and select the critical activities with the condition you have for the criticality (total float less than 5 or total float = 0 or whatever)
This will give you all critical activities listed one after the other.
Im not sure whether this is what you are looking for.
Hi Orozco i am not sure about P3 but could do in a spreadsheet by selecting the activities respective durations followed by early dates .Generally this sort of procedure is called line of balance
Member for
16 years 1 monthRE: Critical Path - Graph like S-Curve
Hi Vishnu...sorry but the requeriment was ask to me bad...the people that ask it only need the S-curve but they have a wrong idea.
thanks
Member for
20 yearsRE: Critical Path - Graph like S-Curve
Hi Orozco,
I dont know if I understood your requirement correctly. Let me put it this way, - you need to have the critical activities one after the other arranged in terms of the early start/ finish dates.
This can be done by
1.Format - organize - Select activity data item - then remove all items under heading group by
2.Under sort by - selct early start or early finish - order by ascend or descend
3. go to filter - and select the critical activities with the condition you have for the criticality (total float less than 5 or total float = 0 or whatever)
This will give you all critical activities listed one after the other.
Im not sure whether this is what you are looking for.
Member for
16 years 11 monthsRE: Critical Path - Graph like S-Curve
Hi Orozco i am not sure about P3 but could do in a spreadsheet by selecting the activities respective durations followed by early dates .Generally this sort of procedure is called line of balance